Department of Communications, Climate Action and Environment

Renewable Energy Generation

Photo of Darren O'RourkeDarren O'Rourke (Meath East, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

15. To ask the Minister for Communications, Climate Action and Environment the figures for all solar installations under all SEAI schemes in Q1 this year, in tabular form; and if he will make a statement on the matter. [18598/23]

Photo of Darren O'RourkeDarren O'Rourke (Meath East, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

18. To ask the Minister for Communications, Climate Action and Environment the average waiting time for solar installation under all SEAI schemes in Q1 of 2023, in tabular form; and if he will make a statement on the matter. [18611/23]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 15 and 18 together.

Below please find a table with the requested information provided by the SEAI:

Applications Received in Q1 2023  Applications Paid in Q1 2023 (1)  Average Time from Application to Approval   Average Time from Approved Application to Receipt of Payment Request for Q1 2023 (4) 
Solar PV  4698  3985  Immediate (2)  121 days 
Community Grants  12  12  No data available (3)  No data available (3) 
One Stop Shops  108  47  Immediate (2)  139 days 
Non-Domestic Microgen  46  N/A Q1  8 weeks  N/A Q1 

  1. Note applications paid in Q1 do not necessarily relate to the applications received in Q1 as it is solely a matter for the applicant to get the works completed once they have an approved application. See note (3) for Community Energy Grants.
  2. For the Solar PV and One Stop Shop schemes – approval of application is immediate once all eligibility criteria are met.
  3. In the case of Community Energy Grants – the approval process relates to the larger community wide project and discrete homes are ultimately only identified to SEAI at time of request grant payment. Hence, in the case of Community Energy Grants, applications and payments relate to the same completed homes.
  4. Note that the average time between application and request for payment is solely a matter for the applicant and their own decisions in respect of scheduling the works with their selected contractor