Written answers
Tuesday, 24 February 2009
Department of Transport
Light Rail Project
11:00 pm
Tommy Broughan (Dublin North East, Labour)
Link to this: Individually | In context
Question 248: To ask the Minister for Transport the estimated completion and opening dates for the extension of the Green Luas line from Sandyford to Cherrywood, County Dublin; and if he will make a statement on the matter. [6974/09]
Noel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context
In May of last year the Railway Procurement Agency (RPA) announced the commencement of the main track-laying contract for the extension of the Luas Green Line from Sandyford to Cherrywood. I understand from the RPA that good progress is being made on the construction of this extension which is scheduled to be completed and operational by end 2010.