Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board

9:30 am

Mr. Phelim Devine:

The fundamental fact is if you are only achieving 60% to 64% of your programme, then for the other 30% to 40% you need more resources to undertake that work. It is really as simple as that. A significant increase in resources is required. There are some really dedicated, really good people on the site working really hard for the children of Ireland, but there just are not enough of them. That is it. The contractor needs to significantly increase its resource if it is to meet its committed date.